Home
|
Construction Project Payne Avenue Water Main Replacement
Location: Walck Road to Meadow Drive
Work: Install approximately 3400 Lineal feet 12" Ductile Iron Pipe Interconnection to all side streets within contract limit New Fire Hydrants New Service Connections
Contractor: E&R General Construction
Construction Contact Telephone Numbers: 695-8565 North Tonawanda Engineering 8:00am to 4:00pm After 4:00pm 695-8535 North Tonawanda Pump Station
Completion of Water Main: 120 Days (August 15th)
Payne Avenue Milling and Paving
Location: Walck Road to Meadow Drive Work: Mill and Pave the entire width of Payne Avenue Bid Date: July 29, 2008 Work to begin: After the completion of the Water Main - TBA Contractor: TBA
|